Technology, AI & Cyber
Google to invest €13bn in Finland AI expansion
Google said Wednesday it will invest at least 13 billion euros ($15 billion) in data centres and other digital infrastructure in Finland to support its artificial intelligence services, including Gemini.
The US technology company called the plan its biggest single investment in Europe. It said the investment also includes clean energy projects over the next two years and partnerships with Finnish companies and the municipalities of Hamina, Kajaani, Muhos and Vaala.
Finland's Prime Minister Petteri Orpo called the investment historic for Finland and said it showed the country had invested in its power grid, electricity production and workforce.
Google has operated in Finland since buying a former paper mill in Hamina in 2009 and converting it into a data centre. Antti Jarvinen, Google's director for Finland, said the Hamina site has already been expanded seven times and currently has seven data centres.
Jarvinen said Google is now expanding in Hamina and opening data centre operations in Kajaani, Muhos and Vaala. He said final numbers on how many new data centres will be built are expected in the coming months.
The construction phase is expected in 2027 and 2028. Google estimated the investment would boost Finland's gross domestic product by 3.6 billion euros annually and support more than 37,000 jobs, including about 16,000 in construction. After construction, Google said the operations would support about 7,000 direct and indirect jobs annually.
Finland has attracted data-centre investment because of its cool climate and relatively stable and cheap electricity from nuclear, wind and hydro power. The expansion has also raised concerns. Grid operator Fingrid has forecast a 40 percent increase in power consumption in coming years, and Finland's Security and Intelligence Service has warned that foreign-owned data centres could pose security risks.
Finnish utility Fortum said Wednesday it had signed a 22-year deal to supply power to Google. Fortum said the agreement would allow it to keep the Loviisa nuclear power plant operating until its licences expire in 2050. Fortum said the plant, which supplies about 10 percent of Finland's electricity, would not have been able to continue past 2030 without that financing.
Update
Google said the plan was its biggest single investment in Europe.
Google's Finland director said the Hamina site already has seven data centres and will expand further.
Google said final numbers for new data centres are expected in the coming months.
Fortum said it signed a 22-year power supply deal with Google linked to continued operation of the Loviisa nuclear plant.
Fingrid forecast data-centre growth could increase power consumption by 40 percent in coming years.
Finland's Security and Intelligence Service warned foreign-owned data centres could raise security risks.
Source note: AFP news report published on 9 September 2026 at 11:21:23 UTC.
Update
Google said the investment includes data centres and supporting infrastructure in Hamina, Kajaani, Muhos and Vaala.
The infrastructure would support Google services including Gemini.
The construction phase is expected in 2027 and 2028.
Google estimated the investment would boost Finland's GDP by €3.6 billion annually and support more than 37,000 jobs, including about 16,000 in construction.
Google said operating the digital infrastructure would support about 7,000 jobs annually after construction.
Source note: AFP news report published on 9 September 2026 at 07:26:42 UTC.
Update
Google said the investment would be at least 13 billion euros over the next two years.
The investment includes data centres to power artificial intelligence models.
Google said the package includes clean energy projects.
Google described it as its largest single investment in Europe.
Source note: AFP news report published on 9 September 2026 at 07:07:37 UTC.
Uncertainty notes
Google said final numbers on how many new data centres will be built are expected in the coming months.
Source
AFP news report published on .